The Korea Aerospace Administration (KASA) and the Korea Aerospace Research Institute (KARI) completed a pre-inspection of the land and sea transport procedures using Nuri rocket 1st, 2nd and 3rd stage mockups, conducted jointly with Hanwha Aerospace, the system integration company for the Nuri rocket, in Suncheon from the 24th to the 26th.

Up until the fifth launch of the Nuri rocket, assembly of each stage and final integration have been carried out at the Naro Space Center in Goheung. However, starting with the sixth launch, the 1st, 2nd and 3rd stages will be assembled separately at Hanwha's Suncheon facility, after which the completed stages will be transported to the Naro Space Center via land and sea routes for final rocket integration in preparation for launch.

This inspection was carried out to verify in advance whether the transport equipment and procedures were appropriate, using 1st, 2nd and 3rd stage mockups before transporting the actual stage assemblies of the sixth Nuri rocket.

/Photo=Hanwha Aero
/Photo=Hanwha Aero

The transport took place on a land section connecting the Suncheon stage assembly site and Yulchon Port, and a sea section from Yulchon Port to waters near Dolsando Island. The process involved mounting the mockups on dedicated transport fixtures, moving them with self-propelled modular transporters (SPMTs), and loading them onto barges for shipment. The actual Nuri stage assemblies are planned to be transported approximately 121 kilometers from Yulchon Port to the Naro Space Center. During this inspection, the transport process was verified by operating a round trip of approximately 80 kilometers from Yulchon Port to the waters near Dolsando Island.

A Hanwha official, speaking by phone with this outlet, stated, "In this transport inspection, Hanwha oversaw the land and sea transport of the stage mockups, while KASA and KARI jointly inspected the transport process and procedures on site." The official added, "Based on the results of this inspection, KASA, KARI and Hanwha will proceed with the transport of each stage of the sixth Nuri rocket without any issues."

Lee Sang-cheol, director of KARI, said, "The process of safely moving a rocket also requires technology accumulated through long-term development and operational experience," adding, "We will thoroughly prepare for the actual stage transport in close cooperation with Hanwha."